Tuesday, 20 June 2017

Progress at the Flat
Building work is all go on the new flat  beside ours, with the plastering and paiinting finished and tiles going down. 
 The tiler is using a electric grinder for the ones that need cutting.
 He only has sunglasses to protect himself from the dust.
 Soon they will be pouring the concrete beams at the top of the gable on Tony and Mary's house,
and the gate across the driveway is up but not secure yet.
 A personnel gate will be added in the gap. A new plinth has been poured for the gate to run along,
 and extra columns have been poured to support the brackets for the top guides.